Melun Hospital specifies KPS piping to fuel diesel heating system

Project Overview

Melun Hospital specified KPS piping to provide a reliable fuel piping system for their diesel-powered central heating system. The designated installer of the project, “AXIMA” is a KPS certified installer and has years of experience working with KPS piping.

Key Requirements

  • A reliable HDPE double-wall piping system to supply diesel to the central heating system.
  • Minimal installation time.
  • Earthing to prevent static buildup.
  • A reliable installer with extensive experience installing the specified piping system.
KPS’ compact electrofusion fittings weld both piping walls simultaneously

The KPS solution

  • KPS 2″ (75/63) and KPS 4″ (125/110) piping proved an ideal long-term solution.
  • 60m coils of KPS 2″ (75/63) conductive piping minimised the number of welds required.
  • Installation was simple and time minimised with KPS’ compact electrofusion fittings which weld both piping walls simultaneously.
  • KPS’ conductive piping creates an electrostatically safe system, preventing potential static charge build-up.
  • KPS’ double wall piping provides an extra layer of protection. All double wall KPS bends, electrofusion fittings and tees also have permeation protection and an interstitial space.
  • KPS liaised with AXIMA, a KPS certified installer to deliver a high-quality installation.
KPS conductive pipes are electrostatically safe
KPS 2’’ (75/63) & KPS 4’’ (125/110) double wall piping provide a safe, easy-install fluid transfer solution
Melun hospital, France specified KPS double wall piping to fuel their central heating system